Project Overview

This project included the addition of a new in ground screenings structure, replacement of master pump station pumps, new grit removal equipment, new 100’ diameter cast in place clarifier, solids removal in oxidation ditches, process piping, and concrete chemical containment structures, electrical, and controls. The new screening channels were 20’ below grade requiring extensive dewatering. Complete bypassing (8.2 MGD) was required for the screening channels, master pump station rehab, and for a portion of the grit removal equipment. Process piping included ductile iron pipe and valves up to 42”. This project was completed in 2016 for $4,711,000.00.