Project Overview
Construction of a new 1.5 MGD WWTF, including a headworks with mechanical screening, grit removal, oxidation ditch aeration, two final clarifiers and two future clarifier structures, chlorine contact tank, parshall flume, aeration cascade, effluent storage, odor control system, site pumping station, chemical building, administration building, maintenance garage, new site development, access road, site piping, electrical, generator, instrumentation and more than 6,400 CY of cast-in-place concrete. With a project cost of $13,638,538, this project was completed in 2012.