Project Overview
Construction of a $5,613,590 expansions to the Gautier WWTF and Escatawpa WWTF including new clarifier, RAS/WAS pumping station, splitter box, sheet piling bulkhead for new concrete basins, new digester, new sludge dewatering facility, sludge pumping station, blowers, piping, and electrical. Project completed in 2010.